en-USes-MX
Ronald Reagan Widening
Location Ronald Reagan Boulevard from FM 3405 to SH 29
Description This project includes making the existing road northbound only and building separate two lanes to act as a second frontage road, which will be southbound only. Both roads will include turn lanes at intersections and shoulders.
Status The engineer, CP&Y, is working on designing the roadway, and anticipates it will be finalized by spring 2021.
Contact Email [email protected] or phone 512-260-4280.
 
Project Map

Map of the project area