CR 200
Location

From CMTA Railroad to CR 201

Description

Reconstruct CR 200 to a two-lane roadway with a center turn lane and shoulders (3 lanes of an ultimate six-lane roadway) a distance of 1 mile.

Status

MA Smith Contracting is the contractor. A groundbreaking ceremony was held on Oct. 27, 2021. Construction is anticipated to begin Nov. 15, 2021, and be completed in fall 2022.

Contact Email [email protected] or phone 512-260-4280
 
Project Maps

Map of CR 200

To view a larger version click the picture. To save right click and click "save picture as"

 
Completed Projects

CR 200 from CMTA Railroad to CR 201 is Project 2 in a three-project improvement effort. Two previous construction projects have been completed along CR 200

Project 1
Improvements at SH29 and CR200/ Loop 332 were completed in summer 2019. The project spanned a distance of 0.2 miles and included adding turn lanes on SH 29, widening CR200 / Loop 332, installing a new traffic, signal, and relocating and isntalling a new waterline.

View Project Map

Project 3
Improvements for CR 200 at Bold Sundown were completed in November 2018. Improvements spanned a distance of 0.2 miles and included widening CR 200 and adding a left turn lane for Bold Sundown.

View Project Map