Design is complete by Atkins. Floodplain impact study is complete. Environmental due diligence is complete. Survey and geotechnical investigation work is complete. A presentation on the project was given at the Brushy Creek MUD Town Hall on April 4, 2019. Meetings with affected property owners were held in November 2018. The construction contract was awarded to DeNucci Contractor, and construction is began in February 2021 and is expected to be complete in late 2021.