Corridor I-1
Location US 183 to Ronald Reagan Boulevard
Description

The first part of the Planning & ROW Preservation Study was completed for a new 1.6 mile-long roadway between US 183 to Ronald Reagan Boulevard with proposed interchanges at each end. The second part of the study is to create preliminary engineering designs for future improvements. Construction will be completed in phases as growth necessitates and funding is secured. 

Status Preliminary engineering design by Atkins is underway. Schematic design with ultimate right-of-way footprint is expected in early 2023. Completion of Phase-1 schematic design for a 2-lane road with turn lanes is expected in summer 2023. 
Contact Email roads@wilco.org/corridorI-1 or phone 512-943-1195.
 
Project Map

Project Map for Corridor l-1