CR 129 (South of Brushy Creek to North of the Southern Williamson County Line)
|
|
|
Description
|
The project will adjust roadway elevation to address sight-distance issues. Williamson County will maintain two lanes in the project area, reconstructing the existing 10-foot lanes as 11-foot lanes and adding two-foot shoulders. The project is being completed as part of the voter-approved 2019 Road Bond.
|
|
|
Status
|
Design was completed by Garver. Right of way appraisals and acquisition are underway and utility coordination is expected to begin later this year. Construction is expected to begin in summer 2023 and be complete in late 2023. To view a project fact sheet, click here.
|
|
|
Contact
|
Email [email protected] or phone 512-943-1195.
|