Bridge Replacement Package I (CR 406, CR 390, CR 427)
This project involved the replacement of three wooden bridge crossings at CR 406, CR 390, and CR 427. The wooden structures at each location were replaced with multiple barrel concrete box culverts to improve the safety conditions of the existing roadway. No major changes were implemented during the course of construction. Construction was complete on November 22, 2002. These bridges are open for public use.
County Road 424 Wooden Bridge Replacement
This project was located on County Road 424 at Turkey Creek. Construction involved the replacement of an existing timber bridge with a multiple barrel concrete box culvert, and reconstruction of the roadway approaches. No major changes were implemented during the course of construction. Construction was complete on January 6, 2004. This bridge and roadway are open for public use.
County Road 412
This project extends from FM 619 to CR 421, a distance of 3.4 miles. Improvements involved reconstruction and widening the existing 2-lane facility to a constant lane width of 12 feet with 4-ft shoulders on both sides. Construction also included asphalt pavement, cross-culverts, driveway culverts, roadside drainage ditches, mailbox replacements, signage, and pavement markings. This was the first project in the Road Bond Program to utilize Geogrid reinforcement material in the pavement section. The Geogrid was added during the construction stages as a method to stabilize the expansive subgrade materials of eastern Williamson County. Construction was complete on August 27, 2003. This roadway is open for public use.
County Road 368 & 369
This project extends along CR 369 from CR101 to CR 366 and along CR 368 from its intersection with CR 369 approximately 1.1 miles north. The net length of this project is 4.3 miles. Construction involved the reconstruction of CR 368 and CR 369E to two12-ft travel lanes with a 2-ft shoulder on each side, as well as the reconstruction of CR 369W to two 10-ft travel lanes with a 2-ft shoulder on each side. Construction also included the installation of drainage culverts, application of a two-course aggregate surface treatment, mailbox replacements, pavement marking, and signage. Final construction of the project included an asphalt overlay in addition to the aggregate surface treatment. This roadway is open for public use.
County Road 300/301
This project included paving improvements on CR 300 from FM 972 south 1.305 miles, a bridge replacement at the intersection of CR 300 and CR 301, and safety improvements including pavement markings and signing at the y-intersection of CR 300 and CR 326. The net project length is 1.737 miles. No major changes were implemented during the course of construction. Construction was complete on January 10, 2004. This roadway is open for public use.
Chandler Road, Phase I
This project extends 2,401 feet west of 1460 east to CR 110, a total length of 2.7 miles. Construction west of FM 1460 includes a 5-lane, curb and gutter roadway with two 12-ft east bound travel lanes, two 12-ft west bound travel lanes, and a 14-ft center turn lane. East of FM 1460, the roadway transitions to a 2-lane undivided facility with 12-ft travel lanes and an 8-ft shoulder on each side. Construction included earthwork, grading, drainage structures, asphalt pavement, obliterating a portion of the existing Chandler Rd. alignment, pavement marking, and signage. No major changes were implemented during the course of construction. Construction was complete on March 26, 2005. This roadway is open for public use. TxDOT is planning a future traffic signal installation at the intersection of Chandler Rd. and FM 1460.
Chandler Road, Phase II
This project extends Chandler Rd. Phase I from CR 110 to FM 1660, a total distance of 5.0 miles. It includes new construction of a 2-lane undivided roadway with 12-ft travel lanes and an 8-ft shoulder on each side. Construction will include earthwork, drainage structures, asphalt pavement, pavement marking, and signage. The facility will also include an overpass at SH 130, comprised of a 76-ft,bridge spanning Chandler Rd. over the SH 130 Toll Road, constructed by TxDOT. Construction of Chandler Road began in September 2006. This project is being constructed by Rodman Construction and has an anticipated completion date of November 2007.
handler Road, Phase 3A
This project extends from FM 1660 to CR 368/369, a distance of approximately 3.1 miles. The design section includes an interim 2-lane facility to match the section currently under construction, with an ultimate design plan for a 4-lane divided section. To date, only preliminary design work has been completed on the project; final design and construction is funded under the 2006 Road Bond Program.
Chandler Road, Phase 3B
This project extends from Phase 3A from CR 368/369 to SH 95, a distance of approximately 4.0 miles. The design section includes an interim 2-lane facility to match the section currently under construction, with an ultimate design plan for a 4-lane divided section. To date, only preliminary design work has been completed on the project; final design and construction is funded under the 2006 Road Bond Program.
County Road 138
This project extends from FM 685 to CR 137. To date, only a preliminary design study has been completed by Halff & Associates. Final design and construction funding of the project has not been allocated.
County Road 112, Phase I
This project extends from Chandler Rd. to just east of FM 1460, a total distance of 1.5 miles. A 4-lane divided urban section with a raised median was constructed extending approximately 1,000 feet south from existing Chandler Rd., adjacent to the Texas State University area campus. From the urban section, the project transitions to a 2-lane rural facility, which continues to the FM 1460 intersection. The project again transitions to a divided roadway through FM 1460, and then back to a 2-lane section where it ties back into existing CR 112 approximately 1,500 feet east of the FM 1460 intersection. The project consisted of new roadway construction, drainage structures, signing and pavement markings. This project utilized Geogrid reinforcement material as part of the pavement section to address expansive subgrade conditions experienced during the construction stages. Construction was complete on August 31, 2005. This roadway is open for public use.
County Road 112, Phase II
This project extends from FM 1460 to CR 110. To date, only preliminary design work has been completed. Final design and construction funding for the project has not been allocated.
Bridge Replacement Package II (CR 351)
Multiple design alternatives have been developed for the replacement of the structure. Final design and construction funding for the project has not been allocated.
Hutto Bypass, Phase 1A
This project extends along CR 119 from the US 79 at FM 685 to existing CR 164, and includes the extension of CR 164 east to1,500 beyond the CR 132 intersection. The total length of the project is 4.9 miles. Existing CR 119 was upgraded from a 2-lane rural facility to include a continuous center turn lane and shoulders. The new segment of CR 164 was a 3-lane section with a continuous turn lane and shoulders. The project also includes ditch improvements along CR 132 and the Hanson Outfall. Construction was complete on July 7, 2006. This roadway is open for public use.
Hutto Bypass, Phase 1B
This project extends from SH 130 to CR 119, a total length of 1.5 miles. The proposed design includes the reconstruction of existing CR 164 from CR 119 to CR 108, the extension of CR 164 from CR 108 to SH 130, and the reconstruction of existing CR 109 (as CR 164) west of SH 130 to Haybarn Lane. The new roadway will be a 3-lane section with a continuous center turn lane and shoulders east of SH 130. The construction will also include an at-grade interchange design with the SH 130 Toll Road and the construction of the CR 109 Spur Road at SH 130. The construction contract has been awarded to Cash Construction, with an anticipated to start date of December 2006 and a scheduled completion date of August 2007.
Hutto Bypass, Phase 1C Schematic
This project extends from CR 110 to Haybarn Lane. The schematic design has been completed by Pate Engineers and the right of way and easement acquisitions are underway. Jonah Water is currently underway with the installation of a new 16" water line along the proposed roadway improvements. Final design of the project is at the 60% stage. Construction funding of the project has not been allocated.
County Road 137
This project extends from 2,200 feet south of CR 138 (which is at the Williamson County Line) to FM 1660, a total project length of 2.2 miles. The project does not include any improvements to the bridge at Brushy Creek. Construction includes widening the existing facility to a standard 2-lane undivided roadway facility with 12-ft travel lanes and 4-ft shoulders on each side, a partial new alignment, ditch and drainage culvert improvements, asphalt pavement, signage, and pavement markings. Construction was complete on October 20, 2005. This roadway is open for public use.
Arterial A, Phase 1
The project limits extend from Joe DiMaggio Blvd. to Forest Creek Drive, a length of approximately 1 mile, and includes the interchange at US 79 and Union Pacific railroad being completed by TxDOT. The design includes the interim 3-lane construction of an ultimate 6-lane facility being developed in coordination with the City Round Rock. The project’s right of way will accommodate future development of pedestrian facilities including sidewalks, hike and bike trails. SD Kallman Engineering is currently working on the design plans, with an estimated design completion date of October 2007.
Arterial A, Phase 2
The project limits extend from Forest Creek Drive to Gattis School Road, a length of approximately 1 mile. The design schematic includes the interim 3-lane construction of an ultimate 6-lane facility being developed in coordination with the City Round Rock. The project’s right of way will accommodate future development of pedestrian facilities including sidewalks, hike and bike trails. SD Kallman Engineering is currently working on the schematic design development, with an estimated schematic completion date of August 2007.
BUS 79 (Taylor)
This project includes the reconstruction, widening and drainage improvements for US 79 through Taylor from W. 2nd St. to Main St. (SH 95), a length of approximately 1.5 miles. Improvements will include widening to a 5-lane section with the addition of a center turn lane, improve drainage to alleviate flooding, installation of curb and gutter and sidewalk, and the replacement of water and wastewater utilities.
US 79 Projects
Section 1 (McNutt Creek to FM 685): The Texas Department of Transportation (TxDOT) will design, fund, and construct this section. County will complete the Environmental Assessment and the Right of Way maps/field notes.
Section 2 (FM 685 to East Hutto City Limit, through town): No work is currently scheduled. The County will fund the design and construction at a later date.
Section 4 (west to Taylor Loop East): No work is scheduled under the current Road Bond Program. The County will fund the design and construction at a later date.