PROJECT UPDATE O'Connor Drive Extension RM 620 to North of SH 45
Oct
27
Written by:
10/27/2011 7:42 AM
Project: 11WC906
CSJ: 0914-05-139
Roadway: O’Connor Drive Extension
Progress for month of October, 2011
Time Charges Began: April 1, 2011
Scheduled Completion Due: Spring, 2012
Work Completed in October:
· Set concrete bridge beams on bent caps
· Placed precast bridge deck panels on beams
· Placed forms for cast in place portion of bridge slab
· Continue to place flex base for roadway
· Backfilled under bridge, placed rock for stabilization
Proposed Work Schedule for November :
· Complete placement of precast bridge deck panels on beams
· Complete formwork for cast in place portion of bridge slab
· Pour bridge slabs
· Place remaining flex base for roadway
· Continue to work on excavation and embankment
· Pour concrete curb for center median
· Remove existing traffic signals and place new signals
· Place conduit for new signals
General Notes:
Contractor is on schedule to complete project in Spring, 2012