Project Update: O'Connor Drive Extension RM 620 to North SH 45
Aug
3
Written by:
8/3/2011 10:50 AM
While our dry weather is bad for lawns, it has been good for road construction! Quite a bit of work has been completed on the O’Connor Drive Extension project, including completing construction of all bridge columns for the bridge at Lake Creek. We also have placed formwork for bridge bent caps on the completed columns as well as poured concrete for bridge abutments, and we have installed box culverts and pipe for cross drainage. Coming up, we will continue to form and pour concrete at the bridge abutments and work on excavation and embankment for the roadway.
Work began June 6 on improvements to the Great Oaks intersection north of RR 620. Currently, we have placed hot mix asphalt for the additional left turn lane, and formed and poured curb and gutter at Great Oaks for the new left turn lane. The work on Great Oaks is scheduled to be completed the week of July 6. Work will begin on the O’Connor roadway improvements north of RR 620 on July 9.
For questions, please contact the road bond hotline at 943-1195 or email roads@wilco.org.
Updates are posted online to http://oconnordrive.org/.